Bronkhorstspruit LL Reservoir

Project Overview

SSI Construction was appointed as a specialist contractor on the Bronkhorstspruit Low Level Reservoir project — a key water infrastructure upgrade aimed at improving storage and supply to the Bronkhorstspruit region in Gauteng.

Working alongside the main contractor Cinderford Construction and the appointed municipal client, we delivered precision formwork and reinforcement services as part of the reservoir’s core structural works, ensuring durability and compliance with stringent engineering standards.


Project Stakeholders

Project Value: R55 Million

Client: Bronkhorstspruit Munipality

Main Contractor: Cinderford Construction

Challenges & Solutions

  • Complex Geometry: Achieved dimensional accuracy using modular and custom formwork panels
  • Tight Schedule: Optimized reinforcement placement sequences and crane scheduling for continuous pours
  • Interface Coordination: Worked closely with civil and hydraulic engineers to ensure seamless integration between reservoir walls, pipelines, and retaining structures